CONFIDENTIAL · STATEMENT OF WORK · V1.4 REVIEW DRAFT
SVZ DesignV1.4 · OCTOBER 7, 2026

CONFIDENTIAL · STATEMENT OF WORK · V1.4 REVIEW DRAFT

SVZ × Utz

2026 CMS, Custom-Variety Experience & AI Search Foundations

Statement of Work: V1.4 review draft, not an executed agreement

Revision date: October 7, 2026

Prepared for: Utz Quality Foods, LLC

Prepared by: SVZ Design LLC

Supersedes: V1.3 (September 17, 2026) for review

Commercial structure: $49,500 fixed fee; 50% at activation and 50% at the approved Day 8 architecture decision gate. Additional work only with prior written approval at $350/hour.

Governing agreement: The framework Master Services Agreement between Utz Quality Foods, LLC and SVZ Design LLC

Signing-to-activation dependency. Day 1 is the first business day after this SOW and the governing MSA are countersigned and the access listed in Section 6 is granted. Every “Day N” means N calendar days inclusive of Day 1. The CMS launch targets December 11, 2026, which holds at Day-45 pacing for a Day 1 on or before October 28, 2026 (countersignature and access by Tuesday, October 27). If activation lands later, SVZ issues a written reforecast within two business days, and Utz and SVZ agree in writing whether the launch date moves or a narrower launch scope ships on December 11. Testing is not compressed to hold a date.

1. Executive summary

On September 21, 2026, Utz asked SVZ to separate the third-party-logistics (3PL) work, now delayed into 2027, and deliver a smaller, standalone 2026 engagement. V1.4 does that by removing deliverables, not by discounting the V1.3 package.

This SOW covers three workstreams on the utzsnacks.com Shopify storefront:

  1. CMS architecture, Salsify alignment and the custom-variety experience, launched as one production release targeting December 11, 2026, the priority Utz set on September 17.
  2. Release QA, launch and bounded stabilization for that release.
  3. A defined technical AEO/GEO foundation: metadata safeguards, a connected brand entity graph, FAQPage and Recipe structured data on agreed templates, a brand-oriented llms.txt resource, and before-and-after measurement.

The 3PL storefront enablement (FBS/Rithum, hybrid Hanover routing, the fulfillment cutover and its support) moves to a separately scoped 2027 SOW, together with the broader optimization items listed in Section 4.

This SOW stands alone. It delivers a complete outcome without any change order, 2027 SOW or other purchase. Everything included here remains SVZ’s delivery obligation unless both parties change it in writing; included work does not roll into a later purchase.

2. Engagement outcomes

Scope is limited to the agreed utzsnacks.com Shopify environment. Other brands may appear as entities in structured data, but no implementation on Zapp’s, Boulder Canyon or other UBI-owned sites is included.

3. Scope of work

Phase 1: CMS architecture, Salsify alignment & custom-variety UX

Window: Day 1 through the Day 45 launch, with stabilization through Day 61. Phase 1 has first call on SVZ capacity through launch.

Activities and deliverables

The Day 8 architecture gate records the exact product types, flow, sample records and acceptance tests.

Milestones

Acceptance

Phase 2: Release QA, launch & stabilization

Phase 3: Technical AEO/GEO foundation

AEO/GEO here means making the included site surfaces clearer to search engines and AI answer systems. It does not guarantee rankings, citations or answer-engine inclusion.

Window: baseline measurement by Day 28, before launch, so Utz has a true before-and-after view; implementation in a follow-on release after the CMS launch, targeted by Day 75 and timed around any Utz holiday change freeze; closeout measurement by Day 90.

Acceptance

Utz supplies and approves the underlying brand, product, FAQ and recipe content. Content production is not included.

4. Moved out of this SOW

4.1 3PL storefront enablement: separately scoped 2027 SOW

4.2 Broader optimization: future scope

These are removed deliverables, not work folded into a lower fee. Any later work needs its own written scope and whatever Utz approvals apply at that time.

5. Timeline

The reference calendar shows October 28, 2026 as Day 1, the latest Day 1 that holds December 11 at Day-45 pacing. The Day column is the commitment; dates move day for day with actual activation, subject to the signing-to-activation clause above. A milestone that falls on a weekend or US federal holiday is held on the next business day.

MilestoneDayReference date
SOW and governing MSA countersigned; access grantedDay 0Tue Oct 27, 2026
KickoffDay 1Wed Oct 28
Architecture/taxonomy decision gate; Invoice 2Day 8Wed Nov 4
Architecture record, mapping specification and design approvalDay 18Mon Nov 16 (Day 18 is Sat Nov 14)
AEO/GEO baseline measurementBy Day 28Tue Nov 24
Release test window, including Thanksgiving weekDay 28 to Day 39Nov 24 to Dec 5
Launch-readiness reviewDay 42Tue Dec 8
CMS production launchDay 45Fri Dec 11, 2026
Weekend Severity 1 monitoringDay 45 to Day 52Dec 11 to Dec 18
Included stabilization window closesDay 61Mon Dec 28 (Day 61 is Sun Dec 27)
Approved extra support ends; AEO/GEO release targetDay 75Mon Jan 11, 2027 (Day 75 is Sun Jan 10)
AEO/GEO closeout measurement; engagement closeDay 90Mon Jan 25, 2027

6. Roles and dependencies

SVZ provides architecture, UX/UI design, theme implementation, release QA, the technical AEO/GEO work, a decision and risk log, and weekly status. Scott Van Zandt is Founder and Executive Sponsor and the escalation point; Keyvon Nariman is the senior client-success lead; Lauren McLaughlin leads operations, scheduling and approvals. SVZ confirms the named delivery owner, Shopify engineering lead, design lead and QA/launch owner in writing at kickoff. Substituting a named lead requires advance notice and equivalent seniority.

Utz provides:

FBS/Rithum readiness does not gate this SOW. Profitero and other vendors keep their own responsibilities and service commitments.

7. Assumptions and exclusions

8. Commercial structure

Fixed fee for the complete scope: $49,500.

InvoiceAmountTrigger
1. Engagement activation$24,750On countersignature of this SOW and the governing MSA
2. Architecture decision gate$24,750On Utz approval of the Day 8 architecture/taxonomy decision gate
Total$49,50050% / 50%

What the fee includes. All deliverables in Section 3, governance, release QA and the 16-hour stabilization allowance.

Additional work. Only with prior written approval (email is sufficient) at $350/hour, with the scope, estimated hours and a spending cap agreed before work starts, invoiced monthly in arrears. Nothing is pre-authorized.

Schedule terms. A delay at the Day 8 gate moves dependent milestones day for day; SVZ issues a written reforecast within two business days, and a reforecast is not a change order. A client- or vendor-caused schedule shift does not reduce the fee or require SVZ to compress testing. Invoice due dates and legal terms follow the governing MSA.

9. Change control

A change request is required when new work materially changes the approved deliverables, product types, flows, templates, integration complexity, data volume, number of releases or schedule. SVZ documents the impact on fee, timing and dependencies, and both parties agree it in writing before the additional work begins.

10. Structured data findings (August 27, 2026 review)

These findings come from SVZ’s August 27, 2026 review of the utz-hyper repository and live storefront. They inform Phase 3 and will be revalidated at activation. The review was non-billable, and SVZ has not changed the storefront.

11. Immediate next steps

  1. Ren reviews V1.4 and returns redlines in Word or in the Slack thread.
  2. Confirm the contracting path: whether this SOW is countersigned together with the framework MSA, or proceeds by another route Utz approves in writing.
  3. Target countersignature and access by Tuesday, October 27, 2026 to hold December 11.
  4. Confirm the specialist approver roster and test-window coverage over Thanksgiving week.
  5. At kickoff, agree the repository baseline and publish path; SVZ confirms the named delivery leads.

Governing agreement

This Statement of Work attaches to and is governed by the framework Master Services Agreement between Utz Quality Foods, LLC and SVZ Design LLC. In the event of a conflict, the MSA controls except as to scope, deliverables, schedule and fees, which are governed by this document.